Slab Load Test
Project Overview
The Slab Load Test evaluates a concrete slab's actual performance by measuring maximum deflection under specified loads, using digital displacement gauges mounted beneath the slab and cement bags as a distributed test load.
Scope of Work
Slab load testing carried out by mounting digital displacement gauges beneath the slab on scaffolding, applying a distributed cement-bag test load, and measuring maximum deflection under specified loads to verify the slab can safely carry its design loads.
When Is a Slab Load Test Needed?
The Slab Load Test is used to evaluate the actual performance of a concrete slab and measure the maximum deflection under specified loads.
Cases That May Require the Test
• Low 28-day concrete compressive strength results and rejected Core test results. • Irregular pours or influential Cold Joints. • Cracks appearing due to loads exceeding the design loads. • Fire exposure that damaged or degraded the concrete slab. • Doubt about the slab's ability to safely carry the design loads.
Project Gallery




Related Articles
Related Projects
Have a project under construction?
We're here to ensure the highest quality and safety standards for your buildings and facilities.
Start your project with us